Build Diary entries for August 2025

Here are the diary entries for this month. You can use the forward and backward links to see the next or previous months. Most photos taken before 2018 are small size. From 2018 onwards, most photos you see below will have a link to a full size image by clicking on the photo.

la Previous Month uparrow Return to 2025 Next Month la
Bogie Centre Slide
18/08/2025
  Highslide JS
  One of our outstanding jobs on the bogie is to make sure that the bogie centre slide can move freely from side to side. First we need to check that the slide moves without the restraining V strips being fitted. Raddle (same as used for marking sheep) has been applied to the bottom of the centre slide (it's upside down in the photo) and then the centre slide is lowered into position on the bogie. When lifted out again, any contact points on the stretcher can be identified. Here Jim and Justin are removing the sharp edges from the lubrication grooves.
   
Cab Window Frames
26/08/2025
  Highslide JS
  The cab window frames arrived today. These have been made in oak by Osset Furnishing of Doncaster.